PWA is not translating to Project and Actual Work Totals

  • Thread starter alysia.m.fields
  • Start date
A

alysia.m.fields

1. MS Project Web Access has data and is saving the data correctly.
But when the Committ Process is completed the information is not
translated to MS Project. It does not happen with all tasks/
resources; it appears to be at random. Why would this happen? How
does one fix it?

2. In one of our Work Plans, the totality of the daily Actual hours
have all summed in one week. Instead of the hours spread out over the
life of the Project, they are added together in one week. It is
occurring under one task, with six resources. Yet the other tasks/
resource appears to reporting normally. Would this have anything to do
with the translating issue noted above? Why and How, on this one as
well.

Thanks
 