R
Ryan
I have a user who is consistently having tasks show up in PWA (in her task
lists) that have been updated to 100% work complete but they are not
updating in the Project. In her task list, it shows 100%, but there is
still the red exclamation in the indicators column that shows that the task
is overdue. When I open the project in Project Pro (on the PM's account),
the tasks show as 0% complete. He is getting notifications when she updates
tasks (we're using a % complete method of tracking) and after he accepts,
the project opens up in Project Professional as if it needs to save changes,
but % complete still shows 0%. The odd thing is that this is not for every
project, some projects update fine.
Thanks for any suggestions,
Ryan
lists) that have been updated to 100% work complete but they are not
updating in the Project. In her task list, it shows 100%, but there is
still the red exclamation in the indicators column that shows that the task
is overdue. When I open the project in Project Pro (on the PM's account),
the tasks show as 0% complete. He is getting notifications when she updates
tasks (we're using a % complete method of tracking) and after he accepts,
the project opens up in Project Professional as if it needs to save changes,
but % complete still shows 0%. The odd thing is that this is not for every
project, some projects update fine.
Thanks for any suggestions,
Ryan