PWA- presenting personal tasks

  • Thread starter דורית
  • Start date
×

דורית

When viewing resources tasks under "View resource assignments", we can see
removed tasks which are not relevant any more.

Is there an option to sort the tasks and not show the ones that were removed
from the project plan?

For example, deleted task in the plan should not apear in the resource's
tasks.

Thanks,
Dorit
 
D

Doug

Dorit:

This is by design. Showing the deleted task lets the user know it was
deleted. Have the user select the task and then select "Hide" from the top of
the timesheet.

If the user does not have the "Hide" option, then they have not been granted
that permission. Have the Project Server Administrator grant them the "Hide"
option

Good luck!
Doug
www.cooltimbers.com
"Art for your soul!"
 