PWA Project Center Grid behavior

K

Kris R.

We have noticed that in a PWA project center grid view that contains project
start/finish dates and baseline start/finish dates, that if you do a group
by owner (for example), the project start and finish dates roll up for each
owner (to be the earliest start date for any project owned, and the latest
finish date for any project owned), but the baseline start/finish don't roll
up. They are just blank.

Is there a way to force the baseline dates to rollup like the start/finish
dates do? (either programmatically, or by some setting somewhere?)

And, in general, how could one ensure such roll up behavior for other
values, such as custom fields, etc? The grid seems somewhat arbitrary in
values that it does roll up automatically...

Thanks,
Kris
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top