Using Project Server 2003 and Project Pro 2003
I have a situation where a tasks start and finish dates have passed and we are trying to book hour to the task. The task is not marked as complete and shows remaining hours. When we attempt to enter actuals on a weekly basis, we get the following message:
You do not have any scheduled during this week.
To Override choose "View Options" and set the "Units" to days then enter your hours on a daily basis.
When we make the requested change, all works well. I guess I'm just confused as to why they are forcing the units to be changed to DAY.
I have a situation where a tasks start and finish dates have passed and we are trying to book hour to the task. The task is not marked as complete and shows remaining hours. When we attempt to enter actuals on a weekly basis, we get the following message:
You do not have any scheduled during this week.
To Override choose "View Options" and set the "Units" to days then enter your hours on a daily basis.
When we make the requested change, all works well. I guess I'm just confused as to why they are forcing the units to be changed to DAY.