PWA Resource Assignments View Not Showing Correct Percent Complete

T

Terry Peters

I have a mismatch between the current task update displayed in PWA Project
Center and in the Resource Center's "View Resource Assignments" page. We
updated % Complete to 100% complete for a task within Project Pro and
Republished the Assignment to PWA. Project Center & Project Details Views
show the task as 100% complete, but the View Resource Assignments Page in
Resource Center shows nothing in the % Complete field. This is true not just
for one resource but it tests the same way for others as well. (The
resources are construction subcontractors in the field who don't actually use
their PWA accounts, so the project manager updates their task percent
complete in Project Pro.) Any ideas about the cause of the failure to update
this particular view?

Thanks in advance from the very grateful,
 
D

Dale Howard [MVP]

Terry --

When you manually enter progress in the Microsoft Project plan, you must do
the following:

1. Click Collaborate - Publish - Republish Assignments
2. Select the "Overwrite actual work entered by resources" option
3. Click OK

The above steps "push" the actuals from the Microsoft Project plan to each
resource's timesheet and into the View Resource Assignments page in PWA.
Did you actually do those steps? Let us know.
 
T

Terry Peters

Dale:
Thanks! I overlooked the need to select the "Overwrite Actual Work" option.
I will see that this is tested and confirm the solution.
Terry
 