PWA Resource Avalability Issue with Ignore Resource Calendar

G

Gary Zag

Using 2007. I have a task that is during the weekend so I have a 7 day task
calendar. The resources's calendar has the weekends as non-working. The
task is set to ignore the resource's calendar. Everything looks fine when
you view the resorces's assignments in PWA. When you go to view the
avalability graph in PWA it does not show the person working the weekend. It
looks like the work is reschedule to a working day.

Is this a bug?

Gary
 
J

Jonathan Sofer

I would not at all be surprise if this is a bug. Have you verified for that
resource that the work is skipping the weekend for that particular project
in the bottom section of the availability screen ? Have you service packed
and rolled up to the latest version? If not, that might help.

Jonathan
 
G

Gary Zag

Yes it does not show work for that weekend in the table below the graph. Am
using latest service pack 1.

Gary
 
Top