This feature is great, but if a resource closes a task during the reporting
week, it will not appear. The PM would like to see a view which shows all the
time entered that week -- even if the task has been completed.

Is there another view that will provide all the time entered by a resource?
Thanks.
 
D

Dale Howard [MVP]

PM Training 12 --

The PM's in question should click the All Assignments link in the sidepane
on the left side of the View Resource Assignments page. Hope this helps.
 
P

PM Training 12

Thanks. Dale. That did the trick.