PWA Showing Incorrect Hours

T

Terry

I have set a day to = 8 hours week =40 hours in the Global Template. But
when I update PWA it shows 7 hour day 35 hour week. If tasks are updated in
PWA project server is updated to the new hours. How can this be?
 
M

Mike Glen

Hi Terry,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top