PWA task view does not display tasks per project

B

Ben

Hi,

PWA task view does not display tasks per project, but each task is presented
as a summary (gray) and then every project having the same task name are
shown under. This strange view is happening only to one resource.

How can I change this to return to the normal view (Every task to a project
under the project summary task name?

Thanks
 
D

Dale Howard [MVP]

Ben --

It sounds like this one user has changed the default Grouping on his/her
timesheet in PWA. Ask him/her to do the following to solve the problem:

1. Log into PWA
2. Click the Tasks menu
3. Click the Filter, Group, Search tab
4. Set the Group By value to Project
5. Set the Then By value to None
6. Click the Filter, Group, Search tab again to collapse the options

Hope this helps.
 
B

Ben

Thanks, problem solved

Dale Howard said:
Ben --

It sounds like this one user has changed the default Grouping on his/her
timesheet in PWA. Ask him/her to do the following to solve the problem:

1. Log into PWA
2. Click the Tasks menu
3. Click the Filter, Group, Search tab
4. Set the Group By value to Project
5. Set the Then By value to None
6. Click the Filter, Group, Search tab again to collapse the options

Hope this helps.
 