I noticed that the tasks in PWA only show work time in HOURS, not DAYS. How
do I change this to show work only in days like in project. Thank you.
 
C

Chris Marriott

Andrew

Create an Enterprise Custom Field [naumber]

Add a formula e.g. a crude formula to derive the number of days when using a
calendar with a working day of 8 hours

[Work] \ 480

Note Project thinks in Minutes for your calculations

Add the new field to the PWA view
--
Regards


Chris Marriott - PMP MCSE MCDBA
UK - EPM Consultant & Trainer
 