On the task view in PWA, when selecting "Notify your manager of time you are
not avail....", how do I globally change the timesheet dates refelected above
to show day and date? It's currently showing only date.

Thanks
 
D

Dale Howard [MVP]

Elena --

Ask your Project Server administrator to do the following:

1. Log into PWA with administrator permissions
2. Click Admin - Customize Project Web Access
3. In the Time Periods section, change the "Number of weeks spanned" value
to 1
4. Click the Save Changes button

Hope this helps.
 
E

Elena

Funny enough I am the administrator and didn't know that. Thanks for your
help!!
--
Elena Espinosa, CAPM
MS Project Server Coordinator



Dale Howard said:
Elena --

Ask your Project Server administrator to do the following:

1. Log into PWA with administrator permissions
2. Click Admin - Customize Project Web Access
3. In the Time Periods section, change the "Number of weeks spanned" value
to 1
4. Click the Save Changes button

Hope this helps.
 