G
Guest
We are currently use the timesheet in PWA to track hours for our
projects. We need to track hours spent on each task on a daily basis.
This forces us to use the "Hours of work done per day or per week:
Resources report the hours worked on each task during each time
period. " method of time tracking. The downside of this method is
that the whole schedule starts shifting around, tasks get split, etc.
if anyone enters even one hour outside the time window for each task
defined in the baseline schedule. I understand that Project is just
trying to adapt to what it perceives as a change of schedule. But the
reality of the situation is that people do jump around on tasks even
though they are linked together in a waterfall method. I tried the
"Actual work done and work remaining: Resources report the actual work
done and the work remaining to be done on each task" method and it
works great as far as not turning the schedule into an unreadable
mess. The downside is I lose the day to day tracking of hours spent
on each task.
So.... my question is: Is there a way to track, on a day-by-day basis,
the hours spent on each task and then have those hours stuffed into
the "actual work" of each task regardless of what day the work was
actually done? Basically I'm looking for a hybrid of the two time
tracking methods I listed.
projects. We need to track hours spent on each task on a daily basis.
This forces us to use the "Hours of work done per day or per week:
Resources report the hours worked on each task during each time
period. " method of time tracking. The downside of this method is
that the whole schedule starts shifting around, tasks get split, etc.
if anyone enters even one hour outside the time window for each task
defined in the baseline schedule. I understand that Project is just
trying to adapt to what it perceives as a change of schedule. But the
reality of the situation is that people do jump around on tasks even
though they are linked together in a waterfall method. I tried the
"Actual work done and work remaining: Resources report the actual work
done and the work remaining to be done on each task" method and it
works great as far as not turning the schedule into an unreadable
mess. The downside is I lose the day to day tracking of hours spent
on each task.
So.... my question is: Is there a way to track, on a day-by-day basis,
the hours spent on each task and then have those hours stuffed into
the "actual work" of each task regardless of what day the work was
actually done? Basically I'm looking for a hybrid of the two time
tracking methods I listed.