B
Botond BAIKA
Hi!
If I use the MS Project client, on any project's any task, I can enter
Actual Work only on work-days. But not on non-working days, like week-end
days for example.
In PWA (Project Web Access), we not have this functionality, but all our
users are screaming for it.
How can I configure PWA to have this functionality (so users can not enter
by any mistake working hours on non working days)?
Or at least, how can I configure PWA to have different colouring for
week-end days?
Thanks, in advance!
Botond
If I use the MS Project client, on any project's any task, I can enter
Actual Work only on work-days. But not on non-working days, like week-end
days for example.
In PWA (Project Web Access), we not have this functionality, but all our
users are screaming for it.
How can I configure PWA to have this functionality (so users can not enter
by any mistake working hours on non working days)?
Or at least, how can I configure PWA to have different colouring for
week-end days?
Thanks, in advance!
Botond