PWA Timesheet Problem

K

Khal

Hey everyone,

I just have a quick question. For some reason, when I
choose the timesheet view in the Tasks page, the amount
worked is always 0, even though I have entered hours for
the given week. Anyone know why?

Thank you.
 
D

Dale Howard [MVP]

Khal --

Where did you enter the Actual Work values? In the timesheet in PWA or in
the Microsoft Project plan?
 
D

Dale Howard [MVP]

Khal --

Are you the project manager or a team member? Are you clicking the Save
Changes button to save the changes on the Server? Are you submitting your
updates to the project manager by clicking either the Update All or Update
Selected Tasks button? Let us know.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"
 
K

Khal

I'm a team member. What I do is I type in a value under
the actual work column in the left pane (I can't type
anything into the right one). Then I click on Save
Changes, then on Update All. Everything else works. The
left pane is updated, the Gantt Chart is updated. The only
problem is that the Timesheet has not information. The
summary tasks and projects all have 0h, and the other
tasks have no information, and the cells are greyed out. I
can't write into them (don't know if that is normal or
not).
 
D

Dale Howard [MVP]

Khal --

What you are seeing is normal in the View my tasks page. Your page is
constructed using your organization's default method of tracking, which
includes entry of information in the Actual Work and Remaining Work columns
on the left side of the page, but does not include the use of the timesheet
grid on the right side of the page. That is why all the cells are grayed
out in the timesheet.

Everything is working as expected. Just keep giving your project manager
your good actuals each week! :)
 
K

Khal

Cool. Thanks for the info!

-----Original Message-----
Khal --

What you are seeing is normal in the View my tasks page. Your page is
constructed using your organization's default method of tracking, which
includes entry of information in the Actual Work and Remaining Work columns
on the left side of the page, but does not include the use of the timesheet
grid on the right side of the page. That is why all the cells are grayed
out in the timesheet.

Everything is working as expected. Just keep giving your project manager
your good actuals each week! :)







.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top