PWA timesheets and administrative projects

S

Simon Dullingham

I've noticed what may be a "feature", but I thought I'd ask if anyone knows
how to fix it:

I have two administrative projects. One is the standard out-of-office
project, the other is an internal project to which we book non-chargeable
(non-Project) hours. The problem is that is you look at PWA, under
"Remaining" it shows all the hours that have been booked to this task since
day 1, and not the hours that are for the future. Actual Hours are never
updated and never show the total booked to the task.

This may be easier to explain with an example.

In the last 18 months (since we install Project Server), I've take 8 days of
vacation (48 hours). Under the "Remaining" column (which is not editable for
an administrative project), it shows 48 hours, instead of 0.

Under "Actual Work", it shows 0. This seems to be completely the wrong way
around.

Any ideas?

Thanks,
Simon
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top