When I get updates from my resources (im the update page)
I want to compre them to the baseline before I accept
them.
How can I add fields to the update page?
Is there a view that I can customize?
Thanks
 
E

Ethan

Use Microsoft Project to check baseline dataUse the Resource
Assignment view (under resource center) where you can see the Status
of as yet unapproved actuals and you can customize the view to include
what ever columns you wish to see such as baseline fields.
 