PWA Views Don't Match!

P

Pete Chrisbacher

Project Server 2003
Project Pro

I recently updated a project plan and published all information to Project
Server. Info updated included actuals and end date (changed from 9/10 to
9/15).

Strangely, I now see two different views of the project in PWA.

In Project Center, the Summary view shows the "old version" of the project
plan - the plan before I made my updates.

If I drill down into the plan by clicking its "Project Name," the "Tasks
Summary" view shows the "current version" of the plan showing the new 9/15
end date and all my changes.

Anyone have any idea what's happening here? How can I fix it?

Thanks -

-Pete
 