I recently updated a project plan and published all information to Project
Server. Info updated included actuals and end date (changed from 9/10 to
9/15).
Strangely, I now see two different views of the project in PWA.
In Project Center, the Summary view shows the "old version" of the project
plan - the plan before I made my updates.
If I drill down into the plan by clicking its "Project Name," the "Tasks
Summary" view shows the "current version" of the plan showing the new 9/15
end date and all my changes.
Anyone have any idea what's happening here? How can I fix it?
Thanks -
-Pete
Project Pro
I recently updated a project plan and published all information to Project
Server. Info updated included actuals and end date (changed from 9/10 to
9/15).
Strangely, I now see two different views of the project in PWA.
In Project Center, the Summary view shows the "old version" of the project
plan - the plan before I made my updates.
If I drill down into the plan by clicking its "Project Name," the "Tasks
Summary" view shows the "current version" of the plan showing the new 9/15
end date and all my changes.
Anyone have any idea what's happening here? How can I fix it?