PWA What is the wright way to indicate non-workin activity

E

Elena

Hi, it's again me and again with questions :)
When team memebers want to indicate non-working time they have 2
opportunities in PWA.
1. On the page TASKS they can choose project "Non-working activity" and put
hours for types of this activity (vacation, sickness, studying ...) Then
press button Refresh.
2. On the page TASKS they can choose "Notification of a leader about time
when you wiil haven't opportunity to work under project" . Come to this page
and on this page in a table put hours for non-working activity.

Questions:
What is the difference between this 2 ways?
What way of notification about non-working activity is correct?

When I use second way, send these, the leader accept all changes in this
projects. Then I go the page RESOURCEs, select myself and ask to show
information about availability I see hours devoted to all types of nonworking
time except vacations (I put hours for vacations, but herу it is empty).

Why does it happen?
When I use 1 way - everything is o'key

Apologize for long explanation
Thank in advance ^)
 
D

Dale Howard [MVP]

Elena --

Option #2 is how you submit planned nonworking time, primarily for vacation
and personal time off. Use option #1 after you return from vacation to
indicate that you actually used the nonworking time. Hope this helps.
 
Top