Hi,

does anybody know what "Synchronize to resource plan" in the PWA 2007 Team
builder does?

Thanks in advance
Paul
 
B

Ben Howard

Hi Paul,
Yes, if you have resource plan associated with a project plan (or
activity/proposal), then this feature allows you to populate the resources on
the project from the resource plan. So, if Todd Rowe exists on the resource
plan, clicking the Sync button will put Todd Rowe on the project. See this
blog for information on doing just that - http://appleparkltd.spaces.live.com
 