D
David A. Cheslow PhD
It's easy enough to report what tasks are SUPPOSED to be worked on between
to dates... but I've had a request for a report of tasks that have actuals
recorded between 2 dates... 'What did we really work on last week?' I've
been able to cobble together an answer using the COM+ add-in that exports to
Excel but it seems like there should be a better way.
Any ideas? Thanks in advance.
P.S. please email (e-mail address removed) as I do not read this group
much anymore.
to dates... but I've had a request for a report of tasks that have actuals
recorded between 2 dates... 'What did we really work on last week?' I've
been able to cobble together an answer using the COM+ add-in that exports to
Excel but it seems like there should be a better way.
Any ideas? Thanks in advance.
P.S. please email (e-mail address removed) as I do not read this group
much anymore.