If by summary information of assignments you mean non-time phased
data, you could check out the MSP_VIEW_PROJ_ASSN_STD table. A catch
however is it is reliant on successful project publishes, being a view
table.
Sorry this table is not worlable for me. If you can tell me how can I
generate a sql using 'Summary' view of Resource-Assignment', it will be very
helpful for me?
Forgive me Ashish, but I'm not sure exactly what you mean by 'Summary'
view of Resource-Assignments. Perhaps the SQL queries for extracting
timephased data included in the SDK would help?