Query related to Microsoft Project Plan

C

Charu

Hello,
I am using MPP for project tracking.
I need the planned and actual dates to appear for each task.
But when I change the actual date of a particular task, the planned date
(i.e. "start" column) also changes, even for the baselined projects.
I want the start and finish dates to be as they were when i baselined the
project even if the i change the actual dates.
Please help me out.
 