D
Dave
I have 2 tasks, both set up the same :
- Duration = 500d
- Type = fixed Work
- % Cmplt=0
- Same start, same finish
I entered one resource (same resource for each)
- Work=100h
Only difference
Task 1 - Units=3% (as expected)
Task 2 - Units = 30% (not sure how this happened)
If I change Duration from 500d to 50d on both:
Task 1 - Units=25% (as expected)
Task 2 - Units = 31% (???)
What the heck is going on here??
Dave
- Duration = 500d
- Type = fixed Work
- % Cmplt=0
- Same start, same finish
I entered one resource (same resource for each)
- Work=100h
Only difference
Task 1 - Units=3% (as expected)
Task 2 - Units = 30% (not sure how this happened)
If I change Duration from 500d to 50d on both:
Task 1 - Units=25% (as expected)
Task 2 - Units = 31% (???)
What the heck is going on here??
Dave