Question about Time Sheeting in Project Server 2007

R

Robert

Hello,

When we create a time sheet and new tasks are added, they don't appear
in the time sheet, you have to manually add them. Is there a way to
get this to work automatically? This could be impossible to keep up
with in some projects with the amount of activity going on. Any
Suggestions? Thanks.
 
D

Dale Howard [MVP]

Robert --

This is a limitation of the new Timesheet feature in Project Server 2007.
You must either delete the Timesheet and then recreate it to capture the new
tasks, or manually insert the new tasks. Hope this helps.
 
B

Ben Howard

The timesheet function was created with a view that most people leave their
timesheets to the end of the week, therefore a "one-click" TS creation
function was deemed suitable, creating a TS with all the current and actual
work for the period imported. Any chance of creating timesheets on a Friday
in your fast moving environment?
--
Thanks, Ben.