Tech.Julio
Hello,
I would like to know if anyone has suggestions on how to come up with a
way to enter in different rates per resource per project. I know I can
set the rate per resource via the resource pool and also set the rate
within project pro, but the resource pool overrides the project when
published. Our contractors' rates are determined by the negotiation
of the contract so the rate always changes.
Thank You,
Julio