Can anyone shed some light on how to add an extra column in Resource Sheet
to give Night Rate in Cost per hour like $20.00/hr. From what i can see there
are already two types in Standard rate and Overtime rate but i would like to
construct another as Night Rate but i am failing miserably, is it not
possible?

Thanks
 
J

Jan De Messemaeker

Hi,

It is not that you cannot show another cost item, you can use one of the
custom cost fields; the problem is that Project will not use this in any
calculation I'm afraid.
HTH
 
W

whatzzup

Thanks Jan

I was not hoping to have project calculate this in my project but marely for
display purposes, it would be benificial if it could form part of my
calculations though.
 