T
TG02
Using the Resource usage view I add the actual hours worked on that specific
day by displaying the actual work field on the right side of the view port
and then adding the number there. I then display the overtime column and then
specify manually how many of the actual hours worked were overtime hours
(anything over 8h per day) by adding that number to the overtime column in
the same row as the task,and project will calculate the overtime cost for me
and add it to the total project cost. This works well.Here is the problem:I
want to be able to do the same thing for weekend hours.The rate for weekend
hours is a higher rate the then regular overtime rate.The problem is that in
the rate sheet there is no option to include another field with a 2nd
overtime rate.I can create a custom cost field and add the weekend overtime
rate to that but that would require a separate Weekend Overtime work and
Weekend Overtime Cost field where I would specify that, of the total actual
hours worked, x amount of hours are weekend hours and need to be calculated
using the weekend overtime rate. This would then need to be added to the
total project cost.Anyone know a workaround to accomplish this. As far as I
can tell ms project does not support this functionality.
day by displaying the actual work field on the right side of the view port
and then adding the number there. I then display the overtime column and then
specify manually how many of the actual hours worked were overtime hours
(anything over 8h per day) by adding that number to the overtime column in
the same row as the task,and project will calculate the overtime cost for me
and add it to the total project cost. This works well.Here is the problem:I
want to be able to do the same thing for weekend hours.The rate for weekend
hours is a higher rate the then regular overtime rate.The problem is that in
the rate sheet there is no option to include another field with a 2nd
overtime rate.I can create a custom cost field and add the weekend overtime
rate to that but that would require a separate Weekend Overtime work and
Weekend Overtime Cost field where I would specify that, of the total actual
hours worked, x amount of hours are weekend hours and need to be calculated
using the weekend overtime rate. This would then need to be added to the
total project cost.Anyone know a workaround to accomplish this. As far as I
can tell ms project does not support this functionality.