A
akphidelt
Hey guys, I'm relatively new to Projects. I looked on Google for the answer
but couldn't find anything.
I work in a remote location where the schedule is 7 days a week 11.5 hours a
day. 8 hours of ST, 3.5 hours of OT.
Also, no matter how many hours you worked in the week, weekends are counted
as overtime. So we get 11.5 hours of Overtime on Saturday and Sunday
regardless.
I worked the Calendars right in my Project, where 2 days = 23 hours in
Duration. But the Cost comes out to $1,380 which is just 11.5 * Straight Time
Rate
My St Time test is $60/hr and Ot is $80/hr
Any thoughts?
Thanks a lot in advance for any help.
but couldn't find anything.
I work in a remote location where the schedule is 7 days a week 11.5 hours a
day. 8 hours of ST, 3.5 hours of OT.
Also, no matter how many hours you worked in the week, weekends are counted
as overtime. So we get 11.5 hours of Overtime on Saturday and Sunday
regardless.
I worked the Calendars right in my Project, where 2 days = 23 hours in
Duration. But the Cost comes out to $1,380 which is just 11.5 * Straight Time
Rate
My St Time test is $60/hr and Ot is $80/hr
Any thoughts?
Thanks a lot in advance for any help.