J
jbecton
In order to limit production downtime, a particular task for my project must
be completed using overtime.
Work = 620 man-hrs
Resource = 6 men at 100% with a normal working schedule of 4-(10hr) days/week.
Project Calendar = 4-(10hr) days/week (Monday - Thursday)
I would like to set up a task without nailing down particular dates (floats
if the schedule changes) to complete the effort by working 12 hr days through
the weekend and into the next week until the task is complete.
What is the best way to structure this task? I attempted to use a task
calendar but couldn't get Project to schedule work on Friday, Saturday, or
Sunday.
be completed using overtime.
Work = 620 man-hrs
Resource = 6 men at 100% with a normal working schedule of 4-(10hr) days/week.
Project Calendar = 4-(10hr) days/week (Monday - Thursday)
I would like to set up a task without nailing down particular dates (floats
if the schedule changes) to complete the effort by working 12 hr days through
the weekend and into the next week until the task is complete.
What is the best way to structure this task? I attempted to use a task
calendar but couldn't get Project to schedule work on Friday, Saturday, or
Sunday.