You simply need to Open the Enterprise Resource Pool and check out the
resources you need to update.
Then simply double click on a resource name to open the Resource Information
dialog.
Choose the Costs Tab and there you'll be able to choose any one of Five Cost
Rate Tables (A, B C D or E) where you can enter costs which can also be
varied over time.
Remember to close and save the changes to the Checked Out Enterprise
Resources, then the next time you log into Project Pro you'll be able to use
the new values and costs will be re-calcualted accordingly.