RBS - Embed/MasterSchedule - confidential rates

C

carbonfins

My security is based on RBS and all my subcontractors are in groups
set exclusively to “The Project Owner has the same RBS value as the
User”.

I would like to be able to embed one contactors schedule into another
and keep resource sheet information (rates) confidential. Is this
possible?

Thanks,

Horton
 
M

Marc Soester [MVP]

Hi Horton,

once a project manager can access MS Project and has access to the global
resource, he/she will be able to see the resource rates. The reason behind is
because the PM needs to manage the Project Cost too. If he/she doesnt know
the cost rate it will make it hard to manage the cost.

I understand your requirement and get this often with my customers. You can
hide the information from PWA users, but not from MS Project users. At least
not without custom dev,
Hope this helps
 