RBS

K

kofiko

I want to add RBS valueto my resources.
How can i do that?
I tried opening the resorce pool , & right clicking a
columm header , but i didn't see the RBS in the pop up
menu...( i understand this is the wayto do it..)
I have built the lookup table .i just want to complete
the rest....
Thanks for any help
kofiko
 
D

Dale Howard [MVP]

Kofiko --

You must create the outline structure of the RBS field in the Enteprise
Global file. You must have Project Server administrator permissions to open
this file for editing. The RBS structure that you create should represent
the "org chart" for your company. Once you have created the RBS field, you
must save and close the Enteprise Global file and then close Microsoft
Project as well.

When you reopen Microsoft Project and log into Project Server, your software
will be "refreshed" with the latest settings in the RBS field. You can then
open the Enteprise Resource Pool file and insert the RBS field in the
Resource Sheet view. With this column added, you can then set an RBS value
for each resource in the Enteprise Resource Pool Hope this helps.
 
G

Guest

Thanks.it did
-----Original Message-----
Kofiko --

You must create the outline structure of the RBS field in the Enteprise
Global file. You must have Project Server administrator permissions to open
this file for editing. The RBS structure that you create should represent
the "org chart" for your company. Once you have created the RBS field, you
must save and close the Enteprise Global file and then close Microsoft
Project as well.

When you reopen Microsoft Project and log into Project Server, your software
will be "refreshed" with the latest settings in the RBS field. You can then
open the Enteprise Resource Pool file and insert the RBS field in the
Resource Sheet view. With this column added, you can then set an RBS value
for each resource in the Enteprise Resource Pool Hope this helps.







.
 
D

Dale Howard [MVP]

Ivor --

To create an RBS field outline code structure, you need to model your
company's "org chart" in the RBS field. For example, a company for which I
used to work might have built the RBS field outline code structure based on
this generic outline:

Corporation
Business Unit
Department
Manager
Team Member

In the company's real RBS code, there would have been multiple Business
Units such as Foods, Grain, Petroleum. Beneath each Business Unit would
have been multiple Departments. For example, the Foods business unit would
have had departments such as Advertising, IT, International Sales, National
Sales, and Production. Depending on your company's organizational
structure, the RBS field outline code structure could be fairly short or
even fairly long.

Once you have created your RBS outline code structure, you will need to
select an RBS value for each resource in your Enterprise Resource Pool.
Doing so will show Project Server "who manages whom" within your
organization. For example, if Gary is at the Department level in the RBS,
and Dale is at the Manager level of Gary's Department branch, and Mickey is
at the Team Member level of Dale's Manager's branch, then Project Server
would infer that Gary directly manages Dale and that Dale directly manages
Mickey. It would also infer that Gary indirectly manages Mickey.

The RBS field is also used in Categories in PWA as a part of Project
Server's security model. If you open any Category for editing in PWA, you
will notice that there is both a Projects section and a Resources section of
the page. In the Projects section, there are four checkbox options when the
second of the two Project options is selected. Several of these checkbox
options are used on conjunction with the RBS. In the Resources section,
there are three checkbox options when the second of the two Resource options
is selected. These three checkbox options are also used in conunction with
the RBS.

That's a general explanation of how things work. For more information about
the RBS and how it fits into the Project Server security model, refer to the
following link to download the Project Server 2003 Administrator's Guide:

http://www.microsoft.com/downloads/...40-147b-447a-b0d3-6088673a53a4&DisplayLang=en

Hope this helps.




Ivor Davies said:
Dale - do you have any examples on how to START setting up an RBS? All the
explanations abouit what RBS does and what it can do for you is fine, but I
need to see how I start creating this table. For example:
1) Do I input a number for each level in the organization.
2) Do I input text for a description of the level or the postion.

It's all very vague to me and I would really like to get this setup since
we are in the PILOT phase of our EPM Project and have only about 50 team
membes and 20 project managers entered into our Enterprise Resource Pool.
 
Top