re-update actual work from web to server

T

Thore Kaalund

Hi
We are using Project server and now after messing around
in the project plan placed on the server the actual work
isn't right anymore.
How can we re-update the actual work from the web ?
Regards
Thore Kaalund
Project Manager
 
L

Lon Swain

Assuming you've set up project server to track time daily
by actual hours, they can re-enter their time in timesheet
view. If you have the actuals in Project Pro 2002, go to
Collaborate / Publish / Republish Assignments. Make sure
you check the "Overwrite actual work entered by resources"
check box. This will republish the actuals to the web
from the project plan.
 