Hello,

We have Project Server 2007.
I assigned a Team leader for 3 tasks.
He want to reassign from Web access one task to one
of the Team members.

He can complete this action only when he reassign resources for all tasks.
How can he reassign only one or several tasks and not all of them ?

Thanks

Pearl
 
K

Kapila Wijethilaka

Hi ,
He can delegate the tasks or he can tell the other person to assign that
taks to himself.

Thanks,
-Kapila
 
P

Perl

Hello,

I don't understand...

The question is why he can't reassign only one task ?

Pearl
 
K

Kapila Wijethilaka

Hi Pearl,

First, He needs to select the task or tasks that he needs to reassign.Then,
he can select the resources that he needs to assign for that task/tasks.

Thanks
-Kapila
 