Hi,

We currently have single server installation of MSPS 2003. We are planning
on seperating the View Processing and Session Mgmt onto a seperate server.
Will we need to uninstall Project Server 2003 off the current server or can
we just remove the View Processing and Session Mgmt components and let the
Project Server 2003 front end component work as is?

Thanks for your help.
NW
 
P

Paul Conroy

You will need to uninstall Project Server off the existing server then:-

Install Views Processing and Session Manager (must do this first)

Install Front-End services (only) onto another server, you will be prompted
for VP/SM machine, re-connect to an existing database.

Don't forget to re-apply the service packs.

Paul
 
N

NW

Thanks.

Paul Conroy said:
You will need to uninstall Project Server off the existing server then:-

Install Views Processing and Session Manager (must do this first)

Install Front-End services (only) onto another server, you will be prompted
for VP/SM machine, re-connect to an existing database.

Don't forget to re-apply the service packs.