In Microsoft project, I owuld like to establish a recurring task that occurs
on the first and third Tuesday of every month. Currently working with
project 2003 standard.
 
J

John

BruceC said:
In Microsoft project, I owuld like to establish a recurring task that occurs
on the first and third Tuesday of every month. Currently working with
project 2003 standard.

BruceC,
You can't do it with a single recurring task but you can do it with two
recurring tasks. To set up a recurring task go to Insert/Recurring Task.
Set up the first group on a monthly basis to cover the first Thursday
and the second group on a monthly basis to cover the third Thursday.

Hope this helps.
John