Recurring task with several parts

S

STeve

Hi
Is is possible to create a recurring task, with several parts. Say, for
example, that every six months, an expense report must be filed on the 1st of
the month, a progress report must be filed on the 15th, and there's a staff
meeting on the 25th. And, the same schedule will repeat, for the next 5
years? Can this somehow be done, with insert recurring tasks?
Thanks
Steve
 
M

Mike Glen

Hi STeve ,

Welcome to this Microsoft Project newsgroup :)

You will have to insert 3 recurring tasks - one for each task.

FAQs, companion products and other useful Project information can be seen at this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials



Hi
Is is possible to create a recurring task, with several parts. Say, for
example, that every six months, an expense report must be filed on the 1st of
the month, a progress report must be filed on the 15th, and there's a staff
meeting on the 25th. And, the same schedule will repeat, for the next 5
years? Can this somehow be done, with insert recurring tasks?
Thanks
Steve
 
S

STeve

Thanks! Is it possible to write a macro, in VB, to change the default working
time from days to months?
Thanks
Steve
 
M

Mike Glen

Good news, STeve! You don't need a macro. Tools/Options.../Schedule tab - Duration is entered in... change to months.

Mike Glen
Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials


Thanks! Is it possible to write a macro, in VB, to change the default working
time from days to months?
Thanks
Steve
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top