Recurring Tasks Error under Project 2007

F

Frank J.

I open a new project, select insert recurring task, give it a task name,
duration, a recurring pattern of "Daily", and a start date/end date.

Project indeeds sets up tasks on a daily basis for the time frame
specified..... However, I also get multiple entries for the same day on some
of the dates (but not all)???

Bug, or am I doing something wrong???

Frank j
 
D

Dale Howard [MVP]

Frank J --

If you specify the Daily option, you also need to select the Workdays option
as well. If you select the Days option, it attempts to schedule recurring
tasks on Saturdays and Sundays, but cannot, so it schedules them on Mondays,
giving three occurrences on Monday. Hope this helps.
 
F

Frank J.

That was it... thanks dale for taking the time to answer my question.

PS: I have (and love) all your books.... got to try doing some more reading
:)

Frank j.
 
D

Dale Howard [MVP]

Frank J --

You are more than welcome for the help, my friend! And thank you for the
kind comments about our books. :)

During the time span between Christmas Day and New Year's Day, I recommend
you read every word in every one of our books! HA!
 