L
Leviathant
I have a question that I have not found a clear answer to via google
groups nor the MS PDF files, and was hoping to get a hand with.
Let's say I have a recurring task that takes 6h over 5d to do,
starting on the 15th of every month. So in the "Recurring Task
Information" box, I set duration to 5d, Recurrence pattern to 15th day
of every month, for 12 months. I let tasks schedule around holidays
and weekends, and now have a recurring task in my task list.
The summary task for the recurring task lists the duration as 243d
with fixed duration. Here's where my question comes in to play. When
I assign a resource to this task with the little People button, it by
default sets them up to have 40h workweeks, being 100% units of a 5d
duration. Currently, I just change the units to a percentage that
comes close to what the actual work hours are.
Is there a more clever way to go about this? I'd like it so that if
the Resource does 6h of work over 5d on this task, the task is then
100% complete.
Thanks;
--matt dunphy
groups nor the MS PDF files, and was hoping to get a hand with.
Let's say I have a recurring task that takes 6h over 5d to do,
starting on the 15th of every month. So in the "Recurring Task
Information" box, I set duration to 5d, Recurrence pattern to 15th day
of every month, for 12 months. I let tasks schedule around holidays
and weekends, and now have a recurring task in my task list.
The summary task for the recurring task lists the duration as 243d
with fixed duration. Here's where my question comes in to play. When
I assign a resource to this task with the little People button, it by
default sets them up to have 40h workweeks, being 100% units of a 5d
duration. Currently, I just change the units to a percentage that
comes close to what the actual work hours are.
Is there a more clever way to go about this? I'd like it so that if
the Resource does 6h of work over 5d on this task, the task is then
100% complete.
Thanks;
--matt dunphy