That may be my problem. I am using 2003 Standard
----- Gérard Ducouret wrote: ----
Hello Art
I checked right now on 2002 version: there is no problem. The recurring tas
rolled up progress *does* transfer to higher level summary bars
Gérard Ducoure
Art Bodiker said:
Anyone know why a recurring task rolled up progress do not transfer t
higher level summary bars