While creating the recurring task you can select the Calendar of the
“Director of Financeâ€. You should assign a Calendar for the Director of
Finance to maintain his or her schedule. Recurring task will be automatically
adjusted as the Resource Calendar is updated.
The Calendar option in the Recurring task dialogue, specifies a calendar for
a task. By default, tasks are scheduled based on the working time of the
project calendar and of resources assigned by their working times. If the
option is set to None, then the task is scheduled based on the project
calendar and on the calendars of any assigned resources. If you apply a base
calendar to a task, as well as resource calendars to the resources assigned
to the task, the task is scheduled during the working time that the task
calendar and the resources have in common.