Hi Helge,

I have been playing with this off and on for the last few days since your
original post. Try as I might, I cannot seem to find a way to make
recurring task bars rollup to an upper level summary bar.

Sorry, maybe someone else has discovered something I have overlooked.

Julie
 
H

Helge Svee

It seems like it can't be done using "Recurring tasks" But I have found my
way around this "problem".

It most easy to use recurring task, but I found my solution but formatting
regular tasks. If I make 5 task and want No 1 to be Summary Task and No2 to
be "recurring task" and No 3 to 5 to be the sub tasks under the recurring. I
mark 3 to 5 and indent them under 2, and check the roll up to summary under
Task Information. For No 2 I indent it under No 1 and for both No 1 and No 2
I check the Show rolled up Gantt bars and Hide task bar in the Task
Information.

This is the solution.