Refusing task in PWA differs from others!?

V

Vitek

Hi All,

If a Resource refuses a task and Team manager accepts this, nothing
will happen in Profi!
X
But when a Resource delegates his task to another Resource2, the field
Resource Names will change correctly.
This is valid for creating new tasks similar.


As for the first paragraph: Is its functionality correct? Is it so on
purpose?
OR What is wrong?


Thanx for your advice.
Vitek
 
G

Gary L. Chefetz

Vitek:

The Team Leader should then reject the assignment to the Project Manager.

--

Gary Chefetz [MVP]
http://www.msprojectexperts.com
"We wrote the book on Project Server"

*** Remember to look for line breaks in links posted to the news group, use
cut and paste for these.
 