Reg Critical Path

S

Sathish

Hi,

I bought a new computer with MS project 2003 installed on it. My
plan is not showing critical path activities in my new computer. If I
open the same plan in my old computer, it shows critical path
activities.

Can anyone tell me what settings can affect critical path.

Thank you

Regards,
Sath
 
J

Jack Dahlgren MVP

The view is the main thing which controls whether you see critical path or
not. Go to the view menu and look at the "Tracking Gantt" to see if a
critical path shows up.
Excessive constraints can also cause your critical path to not show more
than a single task.

-Jack Dahlgren
 
Top