Reimporting a plan and loosing time

P

Paul Douglas

Project manager reimported a project plan. When the resource submitted a
timesheet the prior submitted time reported for that task disappeared on the
project and on the team members time sheet. Does anybody know why this would
happen and is there away to get his already reported time back?
 
D

Dale Howard [MVP]

Paul --

The project manager should do the following:

1. Open the project in question
2. Click Collaborate - Publish - Republish Assignments
3. Select the "Overwrite actual work entered by resources" option
4. Click OK

Doing so will "push" the past actuals onto each user's timesheet in PWA.
Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the books on Project Server"
 
P

Paul Douglas

Dale,

Thank you for the quick reply.

Paul

Dale Howard said:
Paul --

The project manager should do the following:

1. Open the project in question
2. Click Collaborate - Publish - Republish Assignments
3. Select the "Overwrite actual work entered by resources" option
4. Click OK

Doing so will "push" the past actuals onto each user's timesheet in PWA.
Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the books on Project Server"
 
D

Dale Howard [MVP]

Paul --

Thanks for the quick thank you! You are more than welcome, my friend. :)
 
Top