Rejected Task

F

fefe78

Hi all,

Is there any way in Project Professional to know which task has been
rejected or not? I didn't find any field that could help me.

Thanks.

Bye
 
D

Dale Howard [MVP]

fefe78 --

After you apply a task rejection update, navigate to the Task Usage view.
Temporarily insert the Confirmed field. You will see that both the task and
the resource assignment show No for the rejected task. Hope this helps.
 
Top