R
Rob Schneider
Folks,
I've done some Googling on the internet and searching on Microsoft's web
site, with no success.
On my machine at work I have Project 2002 (10.0.2002.0502). I'm having
problems Project incorrectly recomputing Duration when I insert a
subproject file into a linked rollup master file. Both the subproject
and master file are using a specific non-default working-time calendar.
Project is acting as if it forgets the working time calendar. In the
subproject file, for example it's a fixed duration 1-day, but when I put
it into the master file it changes to 1.07 day.
Since I never saw this happen before, I moved all the subproject files
to another machine (my personal machine) running a slightly newer
version of Project 2002 (10.0.2104.1305 SP-1) which I believe is the
most up-to-date version of Project 2002. I see the same problem on the
same master file, but if I recreate the master file, then re-insert the
4 subproject files, the problem does not re-occur.
This makes me think that there was a bug fix between the two versions of
Project 2002. While I can't guarantee this is the root cause of the
problem (more testing is required and I'm short of time), it will help
my cause to request the IT Dept to upgrade to 10.0.2104.1305 SP-1 if I
can show that Microsoft recognised and fixed the bug. Without this, the
IT Dept's attitude will be that I'm doing something wrong since they
will claim that nobody else reports the problem. They don't know much
about Project, and will be hard pressed to really understand the problem.
Anybody recall this particular flaws in Project 2002? A long shot, but
is there a published list of bug-fixes to Project 2002?
Thanks in advance. I have my hands full re-planning a high-profile
project, and I don't have time to mess with what looks to be a bug.
thanks,
rms
I've done some Googling on the internet and searching on Microsoft's web
site, with no success.
On my machine at work I have Project 2002 (10.0.2002.0502). I'm having
problems Project incorrectly recomputing Duration when I insert a
subproject file into a linked rollup master file. Both the subproject
and master file are using a specific non-default working-time calendar.
Project is acting as if it forgets the working time calendar. In the
subproject file, for example it's a fixed duration 1-day, but when I put
it into the master file it changes to 1.07 day.
Since I never saw this happen before, I moved all the subproject files
to another machine (my personal machine) running a slightly newer
version of Project 2002 (10.0.2104.1305 SP-1) which I believe is the
most up-to-date version of Project 2002. I see the same problem on the
same master file, but if I recreate the master file, then re-insert the
4 subproject files, the problem does not re-occur.
This makes me think that there was a bug fix between the two versions of
Project 2002. While I can't guarantee this is the root cause of the
problem (more testing is required and I'm short of time), it will help
my cause to request the IT Dept to upgrade to 10.0.2104.1305 SP-1 if I
can show that Microsoft recognised and fixed the bug. Without this, the
IT Dept's attitude will be that I'm doing something wrong since they
will claim that nobody else reports the problem. They don't know much
about Project, and will be hard pressed to really understand the problem.
Anybody recall this particular flaws in Project 2002? A long shot, but
is there a published list of bug-fixes to Project 2002?
Thanks in advance. I have my hands full re-planning a high-profile
project, and I don't have time to mess with what looks to be a bug.
thanks,
rms