Remaing Work

T

Tim

Hi al,

I have a resource that is on 4 projects, with 100hours of
remaining work. 2 projects that resource is no longer
working, I cleared out his remaining work and expect
remaining to be 50. I open an enterprise resource usage
view project, resource usage view and it is still 100.
However, I then open the projects that I cleared him off,
and now his remaing work = 50. Can anyone tell me what is
going?
thx
t
 
K

Kevin Flanagan

Did you republish the projects after changing the
assignments? You would need to in order for the
assignments to show changes in PWA.

Kevin
 
Top