Can someone explain why MS Project 2007 is giving me a remaining duration of
204.53 days on the Parent when the remaining children tasks, earliest start
is 10/19/2009 and last finish is 12/04/09? The reamaining duration on Parent
should be 32 days (35 business days minus 3 holidays)
Status Date is 10/09/2009
Three tasks 100% complete
All fixed duration
Remaining 4 tasks are all 0% complete, no constraints, and all on same
calendar
Thanks
204.53 days on the Parent when the remaining children tasks, earliest start
is 10/19/2009 and last finish is 12/04/09? The reamaining duration on Parent
should be 32 days (35 business days minus 3 holidays)
Status Date is 10/09/2009
Three tasks 100% complete
All fixed duration
Remaining 4 tasks are all 0% complete, no constraints, and all on same
calendar